Began May 8th, with substantial completion date of May 2024.

  • 575 ft lazy river

  • zero-depth entry area

  • expanded party zone

  • cabanas for private rental

  • terraced seating

  • large island with bridge access

  • support facilities

  • food truck space

  • one speed slide

  • one tube slide

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. 7
  8. 8
  9. 9
  10. 10
  11. 11
  12. 12
  13. 13
  14. 14
JR MARTIN PARK

FARMERS MARKET/COMMUNITY EVENT SPACE @ J.R. MARTIN PARK

The development of a farmers market/community event space at J.R. Martin Park will create a truly unique event space for the City of Republic!  In addition to The Amp (outdoor amphitheater constructed in 2014), Phase 1 of this project will add several improvements to J.R. Martin Park including a large farmers market pavilion, plaza space with seating, food truck space, expanded parking, trail connections to the new space, art elements, and a concession/storage building (if funding allows).  Phase 2 includes an outdoor classroom, unique play elements, and additional art and educational elements.

PROJECT TIMELINE (PHASE 1)

  • Final Design:  June 2023
  • Project Bidding:  March-May 2024
  • Bid Award:  June 2024
  • Construction:  July-October 2024
  • Target Opening Date:   Late Fall 2024/Early Spring 2025  
ATHLETIC COMPLEX

COMMUNITY PARK & REGIONAL ATHLETIC COMPLEX

The development of large community park featuring a regional athletic complex is the largest of our three (3) projects.  The development will take place on 136 acres along James River Freeway. The site already houses a city water tower and will be located adjacent to realigned MM Highway and the Republic School District's new 5/6 Center (pending voter approval).  Phase 1 of this project is slated to include five (5) baseball/softball fields, four (4) soccer/multisport fields, 12 pickleball courts, entry pavilion, retention pond, large areas of green space, support facilities, and parking. Phase 2 of the project is essentially a replica of Phase 1 on the other end of the property.

PROJECT TIMELINE (PHASE 1)

  • Final Schematic Design:  May-July 2024
  • Project Bidding:  January-March 2025
  • Bid Award:  April 2025
  • Construction:  May 2025-February 2026
  • Target Opening Date:  Spring 2026